This is our production building, taking up approximately 30,000 square meters.
Our workshop floors are well equipped with more than 200 skilled employees, 8 production lines, 200 set of computerized sewing machines. With capacity - 100,000pcs complicated backpacks or 200,000pcs simple backpack one month.
Materials preparing (15-20 days)
1. Place order
2. color sample to be confirmed
3. materials production
4. shipping to our warehouse
Cutting (3-5 days)
1. cutting fabric
2. cutting zippers/webbing/silk binding
Packing (3-5 days)